24 November 2026 | Grid & HV | Regulated & Critical Infrastructure
National Grid Electricity Transmission has published a £16.44 million contract award notice naming Costain Limited as the successful supplier for infrastructure upgrades at its Spennymoor 400kV substation in County Durham.
The announcement represents another significant development in the UK’s electricity transmission infrastructure, as investment continues to strengthen network capacity, accommodate new generation connections and support the country’s evolving energy requirements.
The proposed works at Spennymoor include the installation of a new generator connection bay, extension of existing busbar infrastructure, modifications to electrical protection systems and associated substation enabling works.
The anticipated contract period runs from December 2026 to December 2028, with provision for an extension until June 2029.
The project is being delivered through a two-stage Early Contractor Involvement (ECI) arrangement, initially focusing on design development, surveys, planning and pre-construction activities. Contract signature is expected in December 2026, with the subsequent construction phase remaining subject to National Grid issuing a formal Notice to Proceed.
The continued investment in the UK’s electricity transmission and distribution networks presents significant opportunities for engineering contractors, specialist consultancies and the wider supply chain.
However, delivering this infrastructure will require access to suitably qualified and experienced engineering professionals, particularly those with previous experience of working within high-voltage and operational substation environments.
Projects such as Spennymoor could generate recruitment requirements across a range of specialist disciplines, including:
These disciplines represent anticipated workforce requirements rather than confirmed vacancies associated with the project.
With simultaneous investment across electricity transmission, renewable energy, nuclear power, data centres and other critical infrastructure, competition for experienced engineering professionals is likely to intensify.
Within the Grid and HV sector, technical qualifications alone are often insufficient. Previous operational substation experience, relevant safety competencies, National Grid authorisations and BESC Person certification, where applicable, can be important prerequisites.
These specialist requirements can significantly reduce the available candidate pool, making early workforce planning increasingly important for contractors preparing to mobilise major infrastructure projects.
Organisations that develop their recruitment strategies ahead of project delivery will be better positioned to manage skills shortages, programme commitments and mobilisation risks.
At Apex M&E Solutions, our dedicated Regulated & Critical Infrastructure division provides specialist recruitment support to organisations operating within highly technical and regulated engineering environments.
Our sector expertise includes:
We support clients with both permanent and contract recruitment, sourcing experienced engineering, technical and project delivery professionals with relevant sector experience, qualifications and competencies.
As investment in the UK’s critical infrastructure continues, securing the right engineering expertise will be fundamental to successful project delivery.
Is your organisation preparing for an upcoming Grid, HV or critical infrastructure project?
Contact Apex M&E Solutions to discuss how we can support your recruitment requirements, project mobilisation and long-term workforce strategy.